4.1 GENERAL
All high- and low-voltage switchgear is subjected to
extensive tests by the manufacturer before delivery to the customer. While it is not the job responsibility of
operators and maintenance staff to carry out these tests, it is obviously an
advantage to have some knowledge of them.
They are summarised below.
4.2 MANUFACTURERS’ TESTS
Switchgear testing, which is normally taken as meaning
circuit-breaker testing, is a very complex subject, of interest chiefly to
switchgear designers and manufacturers.
Tests fall into two categories, as follows:
(a) Routine Tests
These are tests to which each individual
circuit-breaker is subjected; they comprise the following:
·
Check of
mechanical operation, including measurement of tripping time.
·
Overvoltage
withstand: a test of insulation soundness using a d.c. voltage proportional to
the rated voltage of the circuit-breaker, usually of one-minute duration.
·
Heat run:
a continuous run at full rated current with contacts closed, to check that,
when temperature has stabilised, it does not exceed the specified level.
(b) Type Tests
These are tests made on a prototype circuit-breaker
which is representative of others to demonstrate that the design complies with
the stringent requirements of the system in which it is to operate; these tests
may include the foil owing:
·
Closing
and trip tests at 10%, 30%, 60% and 100% of the rated breaking rms symmetrical
fault current at not more than 0.15 power factor. The breaker must not show ‘distress’, and
there should not be undue contact burning.
·
A trip
test at 100% of the rated breaking peak asymmetrical fault current in one pole
and at more than 0.15 power factor.
·
An impulse
test to simulate the effect of a lightning strike on the system. A steep-fronted, high-voltage pulse rising to
its maximum in 1.2 ms and falling to 50% in not more than
50 ms, is applied. The
circuit-breaker must not trip or flashover.
Trip and impulse tests are carried out at
full voltage and with full fault current.
They call for the use of a large test generator capable of giving out
the full rated breaking MVA without significant drop of voltage. Such test generators are of very special
design and are capable of undergoing repeated short-circuits. There are only a few in the country, located
at special Short Circuit Test Stations.
The largest station in the UK is capable of delivering
6 000MVA. There are also stations
on the Continent of which KEMA in Holland is one of the largest.
All the UK stations are administered by the
Association of Short-circuit Testing Authorities (ASTA). On successfully completing a full type test
they issue an ‘ASTA Certificate’ of rating, which is complete with oscillograms
taken during the test.
Any purchaser of a circuit-breaker of
identical design can obtain a copy of its ASTA Certificate. He would not normally have his own purchased
circuit-breakers undergo repeat short-circuit tests. Only if he had called for any change in the
design which might affect the breaker’s performance and so the validity of the
certificate would new tests and a new certificate be necessary. Such special tests would be extremely
expensive.
The theory of a.c. circuit interruption is
discussed in Chapter 1. The oscillograms
supplied with the ASTA Certificate serve to confirm that the restriking and
other waveforms of the circuit-breaker are in accordance with the design.
4.3 USER CHECKS
Operators and maintenance staff, while it
is not their responsibility to consider the tests referred to above except as a
matter of interest, are required to apply certain routine checks and tests to
circuit-breakers and switchboards at the intervals laid down in the appropriate
maintenance schedules. These tests
include:
·
Visual
examination of the whole switchboard, inside and out, for cleanliness,
mechanical damage, corrosion or signs of overheating or leaking where
applicable. Also checking of busbar and
copperwork for bolt tightness and cleanliness.
·
Megger
testing each part of the switchboard busbar system with all circuit-breakers
open. Tests between each phase and earth
(with the other phases earthed), and between phases.
·
Megger
testing each circuit-breaker in turn (while isolated) between each phase and
earth (with the other two phases earthed), and between phases.
·
Simulation
of overcurrent protection on each circuit-breaker by current injection. This may be of two types - secondary
injection’ or ‘primary injection’ (see para. 4.4).
·
Simulation
of earth-fault, undervoltage or other protection on each circuit-breaker by
manual operation of the protection devices, and checking the alarm indications
and that the circuit-breaker trips.
·
Visual and
electrical checks of the local trip-and-close battery (where fitted) and its
charger(s).
·
Simulation
of trip circuit failure and checking correct operation of Trip Circuit
Supervision with each mode of failure.
·
Taking an
oil sample from each oil circuit-breaker (where applicable) for laboratory
testing at specified intervals.
·
Examination
of the circuit-breaker contacts after a stated period or a stated number of
normal operations, or after a fault clearance.
This includes oil draining where applicable and renewal of oil and of
contacts as necessary.
4.4 CURRENT INJECTION TESTING
Current injection tests are made on switchgear to check
that the various protective systems operate properly and at the correct preset
current levels. Current injection is of
two distinct types, ‘secondary’ and ‘primary’.
4.4.1 Secondary Injection
Secondary injection consists of introducing a variable
controlled current from a separate supply source into the circuit which is
normally fed by the secondary of each current transformer. The CT secondary itself is at the same time
disconnected and short-circuited. Most
relays have a test block with links which enable this to be done without
disturbing the wiring. Varying the
injected current enables the operating settings of the connected relays to be
set up or checked and the continuity of the relay circuit to be verified. Secondary injection does not test the CT
itself.
4.4.2 Primary Injection
Primary current injection achieves a similar object but
consists of injecting a variable but heavy current into the primary of the current transformer;
this avoids disturbing the secondary circuit in any way. As the primary usually consists of a bare
copper conductor bar, connection must be made direct to the bar on both sides
of the CT. In some makes of
circuit-breaker heavy lugs are provided on the bars for this purpose.
The heavy current for primary injection is usually
obtained from a step-down portable transformer fed from the 240V single-phase
station supply. The transformer is
fairly large, about 10kVA, and can supply up to 1 000A of current. Although primary injection has the advantage
that it tests the complete installation, including the CT itself, it is heavy
and cumbersome and is consequently less used in the field than secondary
injection.
Some current transformers are provided with a separate
test winding which is used for primary injection. In that case, instead of injecting a very
large current into the primary bar, a much smaller current can be injected into
the test winding, and the CT itself would still be included in the test. This method, where it can be used, obviates
the need for cumbersome primary injection equipment.
4.5 BUSBAR DUCTER TESTS
Continuity resistance of busbar copperwork, especially
across joints, needs to be regularly checked to prevent overheating. It is measured by a specially-sensitive
continuity tester called the ‘Ducter’ ohmmeter.
This is a portable device, similar to a megger in appearance, but with
an ohmmeter scaled to read down to 1 mW or up to 10 W in six ranges.
This instrument is designed to measure very low values
of resistance while a d.c. test current is flowing. Although principally used for measuring
continuity resistance across busbar joints, it can also be used for measuring
earth bonding and switch and circuit-breaker contact resistance.
The tester is entirely self-contained and incorporates
its own rechargeable battery. The
ohmmeter is scaled 0 - 100 mW, but a 6-way range selector switch extends this up to 10 W. The meter is of the cross-coil
type (similar to that of a megger), which gives a reading independent of the
state of the battery voltage.
The instrument has four terminals: C1 and C2 which apply
test current through the joint to be tested, and two potential terminals P1 and
P2 connected to test prods which are applied either side of the resistance to
be tested. The voltage detected between
P1 and P2 is, by Ohm’s law applied to the known test current, proportional to
the resistance to be measured. This
voltage is amplified within the tester and applied to one coil of the ohmmeter,
the other being fed from the test current.
The meter reads the continuity resistance in microhms direct.
The instrument incorporates a battery tester. If it indicates a low charge state, the
battery must be recharged before use. A
built-in charger enables this to be done from the local a.c. supply
voltage. A completely discharged battery
requires 16 hours to recharge.
In some installations the tests across busbar joints and
joints on other copperwork such as busbar droppers, cable joints and on the
primaries of any wound-type CTs must be carried out with a test current of at
least 20A d.c. The voltage drops so
measured are interpreted on a comparative basis, and for identical types of
connection or circuit the measured values must not differ by more than 20% from
each other.
No comments:
Post a Comment